Dell Technologies
CLIENT: DELL TECHNOLOGIES
Industry: Manufacturing
Description of project:
Dell Technologies – New Customer Solution Centre
- Decommissioning and demolition of the existing plant rooms located at south side of the ground floor.
- Demolition of the existing meeting room.
- Demolition of a section of the existing data center partition walls to facilitate the creation of additional space and for the construction of a number of phone booth style meeting spaces.
- The new CS Center will involve the following;
- Mechanical and electrical upgrades.
- New greeting and reception area.
- New tea station.
- New IOT / Display area.
- New breakout space.
- New meeting / multipurpose room.
- New phone booth type meeting spaces.
- New flooring
- Painting and decoration.
Industry: 750K
Main projects risks:
- Working in a busy manufacturing campus.
- Working adjacent to live workspaces.
- Working adjacent to a live building.
- Restricted working environment.
ASM approach to the management of those risks visa-vie the role we had.
- Project specific risks identified in Preliminary Plan.
- Engagement with the client during the design stage.
- Engagement with the design team
- Engagement with all key stake holders.
Outcome etc.
- Restricted delivery times ( in line with the operations of the Dell campus)
- Traffic management plan for the movement of construction vehicles into and out of the site, and adoption of one-way systems.
- Permitting system when working outside the footprint of the site.
- Erection of temporary hoarding and signage (temporary design)